The ongoing shutdown works at HOJ-11 [Berth No.17(O)] are likely to be completed on 19 June and thus HOJ-11 in all probability will be available for vessel operation w.e.f. 20 June 2022.
Earlier, this office had intimated that the HOJ-1 [Berth No.16(O)] will remain under maintenance from 25 June for a period of 45 days. However, it has now been decided that the HOJ-1 [Berth No.16(O)] will remain under shutdown from 30 June to 17 August.
Source: Haldia Port Trust Trade Circular /1148 dated 16 June 2022