According to a recent publication by the Government Accountability Office (GAO), the U.S. Coast Guard’s Offshore Patrol Cutter (OPC) initiative is encountering significant challenges. Despite years of effort, shipbuilders have yet to deliver any vessels, with costs soaring to an alarming $17.6 billion.
The GAO report highlights that the Coast Guard’s approach of initiating construction before finalizing designs has led to substantial setbacks. Eastern Shipbuilding Group, responsible for the first phase of production, has made little headway since the last evaluation by GAO. Consequently, in July 2025, half of their original contract for four ships was terminated due to insufficient progress. Recently, Eastern announced it would halt work on the remaining two vessels due to severe financial difficulties.
The report emphasizes that “construction of OPCs 1-4 commenced without a stable design,” which deviates from established shipbuilding practices and resulted in delays and rework issues. The delivery timeline for OPC 1 has now been postponed by over five years-from June 2023 to at least late 2026.
Worryingly, Austal USA-the contractor for stage two-seems poised to repeat these mistakes as well. The GAO noted that “construction of OPC 5 began in August 2024 without a stable design.” This raises concerns about potential costly rework and further delays if additional stage two vessels are built under similar conditions.
The financial outlook for this program is grim; costs have escalated from an initial estimate of $12.5 billion up to $17.6 billion due partly to outdated cost data used during planning phases. Furthermore, weaknesses in Austal’s cost tracking systems could hinder effective budget management as construction progresses.
A critical issue arises with stage three procurement strategies; performance testing results from any OPCs will likely not be available before new procurement activities commence-risking premature purchases without confirming whether these vessels meet operational requirements.
The GAO has put forth four recommendations aimed at rectifying these issues: stabilizing designs before further vessel construction begins; enhancing reporting on cost goals; and formulating a comprehensive plan for stage three procurement based on testing outcomes and best practices in shipbuilding methodology. However, only two out of these four recommendations received agreement from the Department of Homeland Security (DHS).
This troubled program comes at a time when there is an urgent need within the Coast Guard for new cutters capable of performing law enforcement duties and search-and-rescue operations effectively as older models age out.
The original strategy envisioned acquiring a total of 25 OPCs across three stages: phase one covering vessels one through four; phase two covering five through fifteen; and phase three addressing sixteen through twenty-five.
Despite its struggles with this particular program, Eastern Shipbuilding recently secured a separate contract worth $714 million for hybrid-electric ferries-a sign that their challenges may be unique to complex Coast Guard projects rather than indicative of overall shipbuilding capabilities.
Meanwhile, Austal USA holds a substantial $3.3 billion contract aimed at producing up to eleven OPCs with plans underway for keel laying its first vessel this December-raising questions about whether lessons learned can prevent repeating past errors as they strive towards delivering essential cutters efficiently.




