Port Dolphins, Mooring Bouys, Piers , Berths , Lighterages and Wharves of Longkou Port

0
198
Port Dolphins, Mooring Bouys, Piers , Berths , Lighterages and Wharves of Longkou Port

 

Terminal Name Berth Name Length (m) Depth (m) DWT Capacity Max LoA (m) Berth Type Shore Cranes Safe Working Load (SWL) Main Cargo Operational Restrictions Safety Features
Longkou Crude Oil Terminal Berth CO-1 350 18.5 300,000 330 Dolphin (4-point mooring) 2 loading arms (16″ diameter) 50 ton (hydraulic) Crude oil (API 15-45) Max wind 12m/s for operations FI-FI 1 firefighting, vapor recovery
Berth CO-2 350 18.5 300,000 330 Dolphin (4-point mooring) 2 loading arms (16″) 50 ton Crude oil Tidal current <1.5 knots Emergency shutdown system
Berth CO-3 300 17.0 150,000 280 Dolphin (3-point mooring) 1 loading arm (12″) 30 ton Crude oil Daylight ops only Oil boom deployment system
Berth CO-4 300 17.0 150,000 280 Dolphin (3-point mooring) 1 loading arm (12″) 30 ton Crude oil Under maintenance until 2024-Q3 Gas detection system
Longkou Product Oil Terminal Berth PO-1 280 15.2 80,000 250 Dolphin (4-point) 3 loading arms (10″) 25 ton Gasoline (RON 92-98) Class I DG zone Overflow protection
Berth PO-2 280 15.2 80,000 250 Dolphin (4-point) 3 loading arms (10″) 25 ton Diesel (10ppm sulfur) Static bonding required Foam fire suppression
Berth PO-3 250 14.0 50,000 220 Dolphin (3-point) 2 loading arms (8″) 20 ton Fuel oil (180-380cSt) Min temp 60°C for transfer Heated pipelines
Berth PO-4 250 14.0 50,000 220 Dolphin (3-point) 2 loading arms (8″) 20 ton Fuel oil Max wave height 1.5m Steam tracing system
Longkou Container Terminal Berth CT-1 350 16.8 100,000 340 Wharf (continuous) 4 STS cranes (ZPMC) 65 ton under spreader Containers Max wind 20m/s (operational) Anti-collision system
Berth CT-2 350 16.5 80,000 330 Wharf 4 STS cranes 65 ton Containers Reefer plugs: 400 available LED lighting system
Berth CT-3 300 15.0 50,000 280 Wharf 3 STS cranes 50 ton Containers Draft limit 14.5m Tandem lift capable
Berth CT-4 300 15.0 50,000 280 Wharf 3 STS cranes 50 ton Containers No OOG cargo Storm bollards
Berth CT-5 250 13.5 30,000 240 Wharf 2 STS cranes 40 ton Containers Feeder vessels only Mobile harbor cranes
Berth CT-6 250 13.5 30,000 240 Wharf 2 STS cranes 40 ton Containers Barge service only Restricted work area
Longkou Bulk Terminal Berth BK-1 300 18.2 180,000 290 Dolphin (4-point) 2 unloaders (2,500tph) 50 ton (grab) Coal (thermal) Dust suppression active Dust monitoring system
Berth BK-2 300 18.2 180,000 290 Dolphin 2 unloaders 50 ton Coal (coking) No simultaneous ops Water spray system
Berth BK-3 280 17.5 150,000 270 Dolphin 2 unloaders (2,000tph) 45 ton Iron ore (62% Fe) Magnetic separators Metal detector
Berth BK-4 280 17.5 150,000 270 Dolphin 2 unloaders 45 ton Iron ore pellets No dust emission Enclosed conveyor
Berth BK-5 250 16.0 80,000 240 Dolphin 1 unloader (1,200tph) 30 ton Alumina Moisture control Pneumatic system
Berth BK-6 250 16.0 80,000 240 Dolphin 1 unloader 30 ton Alumina No rain operations Covered storage
Berth BK-7 200 15.0 50,000 190 Dolphin 1 unloader (800tph) 25 ton Grain (wheat/soy) No insect infestation Fumigation system
Berth BK-8 200 15.0 50,000 190 Dolphin 1 unloader 25 ton Grain (corn) PHST certificate required Moisture control
Longkou General Cargo Terminal Berth GC-1 200 12.0 30,000 190 Wharf (solid) 2 gantry cranes 40 ton (single hook) Steel coils Max coil weight 35t Coil racks available
Berth GC-2 200 12.0 30,000 190 Wharf 2 gantry cranes 40 ton Steel plates Plate size restrictions Magnetic lifters
Berth GC-3 180 11.0 20,000 170 Wharf 1 gantry crane 25 ton Timber logs No bark contamination Log handling gear
Berth GC-4 180 11.0 20,000 170 Wharf 1 gantry crane 25 ton Timber products ISPM 15 compliant Forklift access
Berth GC-5 150 10.0 10,000 140 Wharf 1 mobile crane 15 ton Project cargo Prior notice required Heavy lift area
Berth GC-6 150 10.0 10,000 140 Wharf 1 mobile crane 15 ton Heavy machinery Max cargo height 8m Outsize cargo zone
Longkou LPG Terminal Berth LPG-1 200 12.5 40,000 190 Dolphin (4-point) 2 loading arms (6″) 20 ton Propane Class I DG zone Gas detection system
Berth LPG-2 200 12.5 40,000 190 Dolphin 2 loading arms (6″) 20 ton Butane No open flames Emergency release system
Berth CH-1 180 12.0 30,000 170 Dolphin (4-point) 2 loading arms (4″) 15 ton Methanol Stainless steel piping Double mechanical seals
Berth CH-2 180 12.0 30,000 170 Dolphin 2 loading arms (4″) 15 ton Caustic soda 316L stainless steel Neutralization system
Berth CH-3 150 11.0 20,000 140 Dolphin (3-point) 1 loading arm (3″) 10 ton Specialty chemicals Prior compatibility check Vapor recovery unit
Longkou Ro-Ro Terminal Berth RO-1 200 10.0 15,000 190 Wharf (solid) N/A N/A Vehicles Max gradient 1:10 Fire hydrants every 50m
Longkou Offshore Mooring Buoy MB-1 N/A 20.0 300,000 350 Single buoy (CALM) 1 floating hose string N/A Crude oil 3nm offshore Emergency disconnect system
Longkou Offshore Mooring Buoy MB-2 N/A 18.0 150,000 280 Single buoy (CALM) 1 floating hose string N/A Fuel oil Daylight ops only Oil containment boom
Longkou Lighterage Area Lighterage Zone A 500 15.0 10,000 150 Open water anchorage N/A N/A General cargo Max wave 1.0m Pilot required
Longkou Lighterage Area Lighterage Zone B 500 15.0 10,000 150 Open water anchorage N/A N/A General cargo Daylight only Radar monitoring
COSCO Shipyard Longkou Repair Pier 1 300 12.0 50,000 280 Wharf (solid) 2 gantry cranes 100 ton (main hook)
25 ton (aux)
Ship repair Prior booking required Diving support
Repair Pier 2 250 10.0 30,000 240 Wharf 1 gantry crane 50 ton Ship repair Max draft 9.5m Hot work permitted
Longkou Fishing Terminal Fishery Pier 1 150 8.0 5,000 140 Wharf (solid) N/A N/A Fishery products Sanitary control Refrigerated storage
Longkou Passenger Terminal Passenger Pier 120 7.0 3,000 110 Wharf (solid) N/A N/A Passengers Max 500 pax/hour Security screening
Longkou Emergency Berth Emergency Pier 180 12.0 20,000 170 Wharf (solid) N/A N/A Emergency vessels Priority access Medical facilities
Longkou Barge Terminal Barge Pier 1 100 6.0 3,000 90 Wharf (solid) 1 mobile crane 10 ton Barge operations Coastal service only Tidal compensation

Critical Safety Notes:
1. All oil/chemical berths require:
– Pre-berthing compatibility review
– Emergency towing wires rigged
– Gas-free certificate for hot work
2. Container cranes operational limits:
– Max wind 20m/s (working)
– Max wind 32m/s (survival)
3. Bulk terminals dust control:
– Water spray at 5L/m²/min
– PM10 levels monitored continuously
4. Emergency contacts:
– Port Control: VHF CH 16/12
– Medical Emergency: +86 535 884 9120