In recent days, multiple large LNG carriers at CSSC Dalian Shipbuilding have successively achieved key milestones, with production progress advancing efficiently.
On June 26, the 175,000 cubic meter LNG carrier H5179 commenced sea trials. On June 27, the 175,000 cubic meter LNG carrier H5186 as a complete hull and the H5189 parallel mid-body were simultaneously undocked. Among them, the H5186 complete hull completed the pump tower lifting work 70 days ahead of the company’s annual plan. On the same day, the pump tower lifting operations for cargo holds No. 2 and No. 3 were completed successively, marking the first time in Dalian Shipbuilding’s LNG carrier construction history that the pump tower lifting milestone was achieved within the dock. The H5189 parallel mid-body completed the lifting of four vent masts within the dock for the first time. On the same day, the H5181 parallel mid-body successfully completed the docking and keel-laying milestone.